How many batteries required for 80kva UPS?

10 Mar.,2024

 

To determine how many batteries are required for an 80kVA UPS, you first need to calculate the total power requirements and then determine the battery capacity needed to support the UPS during a power outage.

### Calculate Total Power Requirements:

1. Start by converting the UPS capacity from 80kVA to kilowatts (kW). Since 1kVA is equal to 0.8kW, an 80kVA UPS is equivalent to 64kW.

.

2. Next, consider the efficiency of the UPS system. Typical UPS systems have an efficiency of around 90-95%. To be conservative, assume an efficiency of 90%.

3. Calculate the actual power consumption of the 80kVA UPS by dividing the UPS capacity in kW by the efficiency percentage. .

Actual Power Consumption = 64kW / 0.90 = 71.11kW.

### Determine Battery Capacity:

4. The battery capacity required for a UPS system is typically measured in kilowatt-hours (kWh). To calculate the required battery capacity, you need to consider the runtime needed during a power outage and the discharge rate of the batteries.

5. Determine the runtime required for the UPS system during a power outage. Let's assume a runtime of 30 minutes is needed for the 80kVA UPS.

6. Calculate the total energy needed by multiplying the actual power consumption of the UPS by the runtime needed.

Total Energy = 71.11kW x 0.5 hours = 35.55kWh.

7. Consider the depth of discharge (DoD) of the batteries. For lead-acid batteries, a DoD of 50% is common. This means you should only discharge the batteries to half of their capacity to prolong their lifespan.

8. Calculate the total battery capacity required by dividing the total energy needed by the depth of discharge.

Total Battery Capacity = 35.55kWh / 0.5 = 71.1kWh.

### Calculate Number of Batteries Needed:

9. Finally, determine the number of batteries needed based on the capacity of each battery. Let's assume each battery has a capacity of 2.1kWh.

10. Divide the total battery capacity required by the capacity of each battery to find the number of batteries needed.

Number of Batteries = 71.1kWh / 2.1kWh per battery ≈ 34 batteries.

In conclusion, for an 80kVA UPS system with a 30-minute runtime requirement and considering a DoD of 50%, approximately 34 batteries with a capacity of 2.1kWh each would be required to support the UPS during a power outage.